SPT Installs Nine Suction Piles for Bibby Offshore

SPT Installed Nine Suction Piles for Bibby Offshore345

SPT installed  nine (9) suction piles of OD 5.5-6.5m x 10-11m deep for Bibby Offshore. The suction piles will be used to moor the Ithaca Athena FPSO in 140m water depth.

SPT’s strong SAPS-004 suction pump was used. Actual suction time was only 30 minutes per suction pile. The SAPS-004 suction pump was docked subsea using the ROV. Release was also accomplished following installation by remotely control and monitored by ROV.

[mappress]

Source: sptoffshore , September, 27.  2011;