FPSO and Installation Update on Athena Field Project
The FPSO conversion scope, which is the responsibility of BW Offshore, has proved to be more extensive than was envisaged at the start of the project. In spite of the increase in the amount of work required, BW Offshore and Dubai Dry Docks have completed a fast track engineering project to deliver the vessel very close to the original schedule.
After very recent consultation on health and safety requirements, additional redundancy is being introduced in the vessel power and heading control systems in response to the North Sea incident in 2011 when the Gryphon FPSO suffered a mooring system failure.
The additional work now being undertaken is aimed at ensuring that production startup is not delayed once the vessel has arrived at the Athena field.
Payments for the vessel by the Athena Joint Venture remain unchanged and will commence, by way of a day rate to BW Offshore, only once the FPSO is moored over the Athena field and produced oil is transferred into the vessel’s storage tanks. Once the vessel leaves Dubai, it will sail to the North Sea and hook up to the pre-installed production buoy. In-field commissioning will be minimized by the comprehensive dockside commissioning being undertaken in Dubai.
The journeyto the UK and in-field pre-startup works will take approximately 5 weeks.
Accordingly, the FPSO will remain in Dubai docks to complete all commissioning work and some minor modifications to the
vessel power and heading control systems. It is now anticipated that the vessel will sail from Dubai in early 2012.
The installation of subsea equipment at the Athena field location has progressed well and remains within schedule. The submerged buoy mooring system and all flowlines have been laid and connection is in progress. Installation of the power and control umbilicals and the connection of flexible risers to the riser base and submerged buoy is ongoing and will becomplete well before the FPSO arrives in the field.
Meanwhile, all Athena development wells are now ready for production and the Sedco 704 drilling unit is off contract.
Iain McKendrick, CEO, commented:
“This short term delay is clearly disappointing but it does not change the fundamental value of the project. Athena is a highly valuable development that will more than double net production and further diversify the Company’s production portfolio. Both Ithaca and BW Offshore want to ensure and maintain the highest standards of vessel integrity upon arrival in the field to maximize production uptime and value to the project.”
Joint Venture partners in the Athena field are: Ithaca, operator (22.5%), Dyas UK Limited (47.5%), EWE Aktiengesellschaft (20%) and Zeus Petroleum Limited (10%).
About Ithaca Energy:
Ithaca Energy Inc. and its wholly owned subsidiary Ithaca Energy (UK) Limited (“Ithaca” or “the Company”), is an oil and gas exploration, development and production company active in the United Kingdom’s Continental Shelf (“UKCS”). The goal of Ithaca, in the near term, is to maximize production and achieve early production from the development of existing discoveries on properties held by Ithaca, to originate and participate in exploration and appraisal on properties held by Ithaca when capital permits, and to consider other opportunities for growth as they are identified from time to time by Ithaca.
[mappress]
Offshore Nieuws Staff , December 11, 2011; Image: Ithaca